(01)Project Timeline
Phase
June 2026
July 2026
August 2026
Wk 1
Jun 8–14
Wk 2
Jun 15–21
Wk 3
Jun 22–28
Wk 4
Jun 29–Jul 5
Wk 5
Jul 6–12
Wk 6
Jul 13–19
Wk 7
Jul 20–26
Wk 8
Jul 27–Aug 2
Wk 9
Aug 3–9
Wk 10
Aug 10–16
Wk 11
Aug 17–23
Wk 12
Aug 24–30
Phase 1 & 2 — MVP Pipeline · Contacts · Venues · Sync DataStudios · in UAT now (preview live Jun 2)
Incorporate Feedback & Finalize MVP · Jun 9–20
Milestone Team Go-Live — Off Nutshell DataStudios + HMR · system of record switches
★ Go-Live · Wk of Jun 23
Nutshell → read-only, retire
Phase 3 (was 4) Email & Activity DataStudios · activity log · Gmail · AI summaries · DataChat
Activity Log · Gmail · Compose/Send · AI Summaries · DataChat · Jun 16–Jul 31
Phase 4 (was 3) Reporting & Dashboards DataStudios · commissions · performance · home
Commission Reports · Firm Summary · Designer Performance · Home Dashboard · Jul 13–Aug 29
Phase 5 Sales Goals & KPIs DataStudios · pending revised targets from Jacques
Quotas · % Quota / Go-Get KPIs · TBD
Active Build Phase
Go-Live Milestone
To Be Scheduled
(02)Key Milestones
June 9, 2026
UAT Feedback Window
Preview live since Jun 2 at crm.hmrdesigns.com. Mal & Bob reviewing pipeline, contacts, and venues; feedback gathered over the next several days.
June 20, 2026
MVP Finalized
Last-call feedback plus anything newly flagged is folded in; email/sync polish complete. MVP ready for the full sales team.
Week of June 23, 2026
★ Team Go-Live
Sales team moves off Nutshell onto the new CRM as the system of record. Two-way HMR Direct sync running in production.
June 30, 2026
Nutshell Retired
Set read-only once the team is confirmed active on the new CRM, then wound down. May was the last active month, as agreed.
July 31, 2026
Email & Activity Complete
Phase 3: activity log (notes, tasks, calls, meetings), Gmail integration, compose/send from an event, AI thread summaries, and DataChat.
August 29, 2026
Reporting & Dashboards Complete
Phase 4: per-designer commission reports, firm-wide commission summary, Designer Performance dashboard, and personal Home dashboard.
To Be Scheduled
Phase 5 — Sales Goals & KPIs
Designer quotas plus % of Quota, Go-Get, and Sales Goal KPIs across dashboards. Scheduled once revised targets are confirmed with Jacques.
(03)Sequence & Dependencies
MVP → Go-Live Feedback incorporated and the two-way HMR Direct sync verified end-to-end before the team moves off Nutshell.
Go-Live → Nutshell Retired Team confirmed active on the new CRM before Nutshell is set read-only and the subscription is closed out.
Phase 3 runs alongside Go-Live Email & Activity is built from mid-June onward; designers connect their Gmail as they onboard to the CRM.
!
Phase 3 before Phase 4 (re-sequenced) Email & activity is now prioritized ahead of reporting — a change from the May 5 plan, where commissions/dashboards came first.
Phase 4 → Phase 5 Reporting & dashboards ship before sales-goal KPIs, which depend on revised targets and quota structure.
!
Open input — Jacques Phase 5 scope (quotas, sales goals) is blocked pending updated numbers from Jacques; timing stays TBD until then.