(01)Project Timeline
Phase
June 2026
July 2026
Wk 1
Jun 1–7
Wk 2
Jun 8–14
Wk 3
Jun 15–21
Wk 4
Jun 22–28
Wk 5
Jun 29–Jul 5
Wk 6
Jul 6–12
Wk 7
Jul 13–19
Wk 8
Jul 20–26
Wk 9
Jul 27–31
Phase 0 Re-Import & Delta Sync Setup DataStudios
Phase 0 — Re-Import & Sync
Phase 1 UAT Wave 1 — Sales Manager Tyler Kopp  ·  tyler@cremecollective.com
Phase 1 — Tyler Kopp  ·  Jun 9–20
Phase 2 UAT Wave 2 — Sales Lia Briehl  ·  lia@cremecollective.com
Phase 2 — Lia Briehl  ·  Jun 16–27
Phase 3 Data Validation (Parallel) DataStudios  ·  Concurrent with Phases 1–2
Phase 3 — HubSpot Parity Validation  ·  Ongoing Jun 9–Jul 5
Phase 4 Blue-Green Overlap Window DataStudios + Crème  ·  5-day parallel run
Phase 4 — Blue-Green  ·  Jul 6–12
Phase 5 Cutover Day DataStudios + Crème  ·  4-hr rollback gate
★ Cutover — July 14, 2026
Phase 6 Post-Cutover Stabilization DataStudios  ·  2-week support window
Phase 6 — Stabilization  ·  Jul 14–31
Active UAT Phase
Parallel Validation
Blue-Green Window
Cutover Day
Stabilization
(02)Key Milestones
June 1, 2026
Project Kickoff
Full HubSpot re-import: contacts, companies, deals, activities. Delta sync (15–30 min pull) configured and tested.
June 6, 2026
Sync Confirmed
24h of delta events verified in sync log. Initial parity spot-check passes. UAT Wave 1 cleared to begin.
June 9, 2026
UAT Wave 1 Opens
Tyler Kopp begins 10-scenario validation. DataStudios attends first 1–2 sessions, then async feedback form.
June 16, 2026
UAT Wave 2 Opens
Lia Briehl begins sales-specific scenarios. Tyler Kopp handles peer onboarding. Waves overlap by 1 week.
June 27, 2026
UAT Complete
Both waves sign off. All P0/P1 issues resolved or triaged. P2 items deferred to post-cutover backlog.
July 5, 2026
Validation Sign-Off
Parity scorecard ≥ 95% across all objects. DataStudios + Crème stakeholder co-sign required to advance.
July 6, 2026
Blue-Green Opens
5-day parallel window. HubSpot = blue (active input). CRM = green (sync target). No CRM writes back to HubSpot.
July 14, 2026
★ Cutover Day
CRM becomes system of record. HubSpot restricted to read-only. 4-hour rollback gate active. Stabilization begins.
(03)Phase Dependencies
Phase 0 → Phase 1 Re-import complete and 24h of sync events confirmed before Tyler Kopp begins UAT on June 9.
Phase 1 → Phase 2 Tyler completes 80%+ of Wave 1 before Lia onboards. Overlap of 1 week (Jun 15–21) is intentional — Tyler peer-onboards Lia.
Phase 1 + 2 + 3 → Phase 4 All three must reach sign-off before the Blue-Green window opens July 6. No exceptions.
Phase 3 runs in parallel Validation starts June 9 alongside Phase 1. Daily automated count comparison + spot-checks. Final scorecard due July 5.
Phase 4 → Phase 5 5 consecutive clean days in Blue-Green (no sync failures, no P0 data issues) required before Cutover Day is confirmed.
!
Rollback Gate (Phase 5) P0 within 4 hours post-cutover: revert HubSpot to active, freeze CRM writes, reschedule. Phase 6 only after gate clears cleanly.